On May 15, construction will begin or enter new phases on projects throughout the Clemson University main campus. Several of these projects will impact parking, transportation and access to the surrounding areas.
- For an overview of these summer construction projects, including impacts, maps and renderings, visit the University Facilities Summer Construction 2023 StoryMap.
- For up-to-date information on these and other construction projects, visit the University Facilities Construction Map.
Projects and Key Dates
Building Projects
- Women’s Sports Program Expansion
- May 15–February 2024
- Advanced Materials Innovation Complex
- Impacts
- Phase I: May 2023–June 2023
- Phase II: June 2023–August 2023
- Phase III: August 2023–End of 2025
- Daniel Hall Renovation and Expansion
- Ongoing; projected completion August 2023
- Byrnes Hall Renovation
- Access impacted
- May 15–July 2024
- Life Sciences Atrium Renovation
- May 15–mid-August 2023
- Forestry and Environmental Conservation Building
- Parking impacted
- May 15–July 2025
- Development and Alumni Center
- Access to Lake Drive affected
- Ongoing; expected building completion September-October 2024
Road Construction Projects
- Perimeter Road Widening
- Traffic patterns
- Ongoing–mid-October 2023
- Williamson Road Re-alignment
- Section closed from Perimeter Road and S. Palmetto Blvd.
- May 15–August 2023
- Fernow Street Repaving
- Single lane only through June 2023
- Kappa Street Parking Improvements and Repaving
- Road closed: May 15–mid-August 2023
- Jersey Lane Repaving
- Road closed: July 1 for two weeks
Other Projects
- Memorial Stadium Renovations – Phase II
- Ongoing–August 2023
- C-2 Parking Lot Expansion
- May 15–June 2023
- South Campus Stormwater & Landscaping Improvements – Suber Dam
- Ongoing–March 2024
- Cooper Parking Lot (West) ADA Improvements and Repaving
- Lightsey Bridge/Commons Court Parking Expansion
- May 15–September 2025
- P-5 Parking Lot Expansion
- May 15–September 2023
- Campus-Wide Steam Outage
- May 15-18