On May 15, construction will begin or enter new phases on projects throughout the Clemson University main campus. Several of these projects will impact parking, transportation and access to the surrounding areas.

Projects and Key Dates

Building Projects

A rendering of the new Clemson Alumni and Visitors Center
A rendering of the new Clemson Alumni and Visitors Center
  • Women’s Sports Program Expansion
    • May 15–February 2024 
  • Advanced Materials Innovation Complex
    • Impacts
    • Phase I: May 2023–June 2023
    • Phase II: June 2023–August 2023
    • Phase III: August 2023–End of 2025
  • Daniel Hall Renovation and Expansion
    • Ongoing; projected completion August 2023
  • Byrnes Hall Renovation
    • Access impacted
    • May 15–July 2024
  • Life Sciences Atrium Renovation 
    • May 15–mid-August 2023
  • Forestry and Environmental Conservation Building
  • Development and Alumni Center

Road Construction Projects

Perimeter Road diagram with text: "The Perimeter Rd. project spans 1.5 miles of roadway between HWY 76 and Williamson Rd."
  • Perimeter Road Widening
    • Traffic patterns
    • Ongoing–mid-October 2023
  • Williamson Road Re-alignment
  • Fernow Street Repaving
    • Single lane only through June 2023
  • Kappa Street Parking Improvements and Repaving
    • Road closed: May 15–mid-August 2023
  • Jersey Lane Repaving 
    • Road closed: July 1 for two weeks

Other Projects

A rendering of the completed Phase II of Memorial Stadium
A rendering of the completed Phase II of Memorial Stadium
  • Memorial Stadium Renovations – Phase II
    • Ongoing–August 2023